What data should be available during the completion acceptance of membrane structure?
Release time:
2021-09-15
A. Design drawings, as built drawings, drawing review records, design change documents.
B. Construction organization design and technical disclosure records.
C. Ex factory quality certificates and re inspection reports of materials. Including: raw material inspection, membrane inspection, connector inspection, lower support structure and embedded parts inspection report.
D. Construction inspection records, concealed works acceptance records, processing and installation self inspection records, membrane structure ridge and valley cable tension value records, and tensioning travel records.
E. Acceptance records of subdivisional works.
Relevant news

Free access scheme
FOLLOW US

Anhui liteng membrane structure Engineering Group Co., Ltd
Company: 17th floor, building C, minshang International Trade Center, No. 277, Changjiang East Street, Yaohai District, Hefei, Anhui, China
Factory: intersection of prosperous Avenue and Longxing Avenue, Feidong County, Hefei, Anhui, China
E-mail:1966891005@qq.com
website:www.sinoliteng.com
This website fully supports the relevant provisions on "limiting prohibited words" implemented in the Advertising Law of the People's Republic of China, and has tried to avoid the use of "prohibited words". Therefore, from now on, any text or picture on any page of this website that contains the introduction of limiting "prohibited words" is not the subjective intention of this website and will immediately become invalid, and cannot be used as a reference basis for any behavior of customers. All visitors who visit this website agree with this treaty! Thank you for your cooperation